๐ Project Steering Committee Meeting #8
ALT Platform Development (Unified WE/MWE Mobile App)
Date: Tuesday, 6 January 2026
Time: 4:30 PM (Myanmar Time)
Meeting Type: Steering Committee
Facilitator: Thu Yain Htut (Project Director, GCA)
1. ๐ฏ Objectives
- Review Phase 2 development progress (Sales & Financial Flows)
- Confirm UAT readiness and schedule for Phase 2
- Review Deliverables Roadmap (with UAT & Bug Fix windows)
- Confirm mobile device requirements for procurement
- Align next steps for Phase 3 preparation
2. ๐ฆ Overall Project Status
Status: ๐ก On Track (Phase 2 in execution)
- Phase 1 is completed and stabilized
- Phase 2 development is in progress, focusing on sales workflows, collections, and payments
- UAT and bug-fix periods are now explicitly planned per phase to reduce Go-Live risk
- Overall Go-Live target remains late April 2026, subject to phase validation
3. ๐ Phase 2 โ Current Progress Overview
โ Completed / Stable
- Product catalog & category integration
- Sales order creation flow (mobile โ Odoo)
- Cash down-payment handling
- Batch number automation (approved change request)
๐ In Progress
- Partial payment handling
- Automatic invoice & payment flow (Odoo side)
- Mobile sales workflow refinement
โณ Planned (Phase 2 Scope)
- Sale order listing & filtering
- Payment function (mobile)
- Offline queueing for sales-related actions
- Phase 2 dashboards
4. ๐ Timeline & Roadmap Alignment (Deliverables Roadmap v3)
Phase 2 โ Sales & Financial Flows
- Development: Dec 1, 2025 โ Jan 23, 2026
- UAT & Bug Fix: Jan 26 โ Feb 6, 2026
Phase 3 โ Inventory Ops & MWE Oversight
- Development: Feb 1 โ Mar 6, 2026
- UAT & Bug Fix: Mar 9 โ Mar 20, 2026
Version 1.0 Release
- Soft Launch (Pilot) - 1 to 2 months
- Launch with few users
- Actual Launch - Gradually
- Launch with all users
Phase 4 โ Activities & Surveys
- Development: Mar 9 โ Mar 27, 2026
- UAT & Bug Fix: Mar 30 โ Apr 10, 2026
Version 2.0 Release
- Final UAT, Training & Deployment: Apr 13 โ Apr 24, 2026
- Target Go-Live: Late April 2026
5. ๐งช Phase 2 โ UAT Planning
Proposed UAT Scope
- Sales (cash & credit)
- Collections & partial payments
- Payment posting to Odoo
- Offline โ online synchronization
- Sales reports & dashboards
UAT Participants
- ALT internal users (no WEs at this stage)
- GCA support team
Key Agreement Needed
- Confirmation of UAT start date
- Confirmation of acceptance criteria for Phase 2 sign-off
6. ๐ฑ Mobile Device Requirements (Procurement Readiness)
Proposed minimum requirements (pending final confirmation):
| Category | Requirement |
|---|---|
| RAM | 8 GB or higher |
| Storage | 256 GB internal storage or higher |
| OS | Android 15 or later |
| Region | Global compatibility |
Arkar Phyo to confirm final storage estimates (including offline usage impact).
500 KB estimated per photo x No. of Photos per upload x no. of transactions per customer
7. ๐งญ Development Coordination & Risk Management
Identified Risks
- Offline feature complexity
- Late UAT feedback affecting downstream phases
- Device constraints for offline storage
Mitigation Measures
- Phase-based UAT & sign-off
- Weekly validation meetings
- EPIC-level progress tracking
- Scope freeze after phase approval
8. ๐๏ธ Governance & Meetings
- Weekly follow-up meeting: Every week at 2:30 PM (MMT)
- Next Steering Committee Meeting: To be confirmed (mid-January)
- Progress updates to be shared in advance of committee meetings
9. ๐งฉ Action Items
Meeting #7
| Action | Owner | Due Date |
|---|---|---|
| Finalize and share updated delivery timeline together with Phase 4 and Phase 5 | Arkar Phyo | Done |
| Finalize mobile device storage calculations | Arkar Phyo | Can reduce lower than 1 MB of each photo. multiply by no. photos and no. of transactions per day |
| Prepare EPIC-level progress overview (Screenshots) | Thu Yain Htut & Arkar Phyo | EPIC level progress screenshots will send starting next week |
| Prepare training materials for soft launch | Khun Ye Lwin Htoo | Before soft launch |
| Categorize and prioritize remaining Phase 1 bugs | Arkar Phyo | Ongoing |
| Update documentation and circulate minutes | Thu Yain Htut | Done |
| Confirm next Steering Committee meeting | Thu Yain Htut | Done |
@Arkar to have workshop on photo saving mechanism with the dev team and propose the solution to optimize the data storage on mobile as well as cloud server | Arkar Phyo | Can reduce lower than 1 MB of each photo. multiply by no. photos and no. of transactions per day |
additional server that we need to buy, was its size estimated | Arkar Phyo | 500 KB x no. of photos per transaction x no. of transactions per day |
Meeting #8
| Action | Owner | Due Date |
|---|---|---|
| Confirm Phase 2 UAT start & criteria | ALT | next committee meeting |
| Continue Phase 2 development | GCA | Ongoing |
| Prepare Phase 3 technical outline | GCA | Before Phase 2 UAT end |
To Confirm Survey Field Type | Ko Ye | Next Meeting |
Version 1.0 Release Preparation in timeline | Arkar | Next Meeting |
To send storage calculations in excel to ALT team | Arkar | 8 Jan |